Former President Donald Trump says numerous issues that aren’t true. One latest “various truth” associated to electrical automobiles was so off that we felt the necessity to appropriate the file. No, this isn’t about politics or the upcoming election; it’s simply what we do. When individuals spew nonsense about EVs—or on this case, EV charging—InsideEVs claps again and brings receipts.
In no less than three latest speeches—together with his tackle on the Republican Nationwide Conference and at rallies in North Carolina and Atlanta—Trump stated that President Joe Biden’s administration has spent $9 billion on “eight chargers.”
It’s an eye-popping determine, for positive. And it’s additionally fully false. Even when you take that to imply eight charging stations quite than eight particular person chargers, that’s a gross exaggeration.
EVs get political
Electrical automobiles have change into a punching bag for Republican presidential nominee Donald Trump and his operating mate, J.D. Vance. Each have proposed chopping funding for EV-related insurance policies.
The mathematics positive sounds absurd—a few billion {dollars} for one charger—however what regular individual really is aware of how a lot a charging station ought to value? Why ought to they? In an election cycle that’s seen EVs get extra politicized than ever, you, the individuals, should know the info.
So let’s dive into what’s incorrect right here—and the tiny kernel of reality on the middle of Trump’s outrageous declare.
A GM Power charging station.
How Many Federally Funded EV Chargers Have Been Constructed?
What Trump is referring to, it might appear, is the Nationwide Electrical Car Infrastructure (NEVI) program, which was established by the 2021 Bipartisan Infrastructure Regulation. This system put aside $5 billion in federal funds to blanket the nation—notably its main highways—with hundreds of latest DC fast-charging stations.
NEVI and the associated $2.5 billion Charging and Fueling Infrastructure Grant program are essential as a result of a scarcity of reliable charging stations is likely one of the greatest issues amongst would-be EV consumers.
It’ll turn out to be useful to know the very fundamentals of how the NEVI program works. States apply for federal funding, then put out requests for proposals for the tasks they need carried out. Charging firms like Tesla and BP bid on the tasks and deal with building and operation.
NEVI runs by 2026, with a piece of the overall funds going out to states annually till then. Up to now, all 50 states plus Washington, D.C. and Puerto Rico have obtained a complete of roughly $2.4 billion, in accordance with the U.S. Joint Workplace of Power and Transportation, which helps NEVI and different clear transportation initiatives.
It’s true that nearly three years after NEVI was handed, solely a handful of places have come on-line. But it surely isn’t “eight chargers.” Up to now, 15 NEVI-funded charging stations have opened for enterprise, offering 61 particular person EV chargers to drivers throughout eight states, a spokesperson for the Joint Workplace stated. The primary station opened in Ohio in December, adopted by websites in New York, Rhode Island, Pennsylvania, Utah, Hawaii, Maine and Vermont.
Which will sound gradual, however Gabe Klein, the workplace’s government director, informed InsideEVs that the rollout is continuing at concerning the price he had anticipated.
“We reside on this 24-hour information cycle with social media and we simply assume, ‘Hey, you go a invoice after which subsequent yr there are chargers.’ And that’s simply not the way it works when you’re speaking about constructing out main infrastructure,” he stated. “It’s really going rather well, and we’re about the place we thought we’d be.”
Erecting high-powered charging stations doesn’t occur in a single day, and it is extra sophisticated than putting in a slower plug in a storage or parking zone. It takes 18-24 months simply to deliver energy to a DC quick charger from the purpose the utility is notified, Klein stated. Plus, it takes time for states to design tasks, solicit bids and get issues transferring, notably after they’ve by no means needed to construct EV chargers earlier than, he stated. These processes are getting extra environment friendly as time goes on, Klein stated.
“For those who’re used to constructing bridges and highways, and now you’re chargeable for constructing out a charging community, there’s a studying curve,” he stated.
A Tesla Supercharging station.
Klein stated that NEVI charger deployments ought to take off within the coming months and years. He expects the variety of plugs within the floor to climb to a whole bunch by the tip of this yr and hundreds in 2025. Installations ought to peak round 2027 or 2028, he stated.
Did 8 Chargers Actually Price $9 Billion?
So “eight chargers” is bunk regardless of the way you slice it. However how a lot do these stations value? Trace: It’s not $9 billion for eight chargers.
The primary part of the NEVI program intends to fill main gaps within the nation’s EV infrastructure by inserting stations at 50-mile increments alongside key corridors. In response to the Joint Workplace’s evaluation, that may require 1,537 places with 9,222 complete plugs, assuming six plugs per station. The full value for that, the workplace says, can be roughly $1.1 billion.
Factoring in tools, set up, 5 years of upkeep and station-related prices, the Joint Workplace estimates the price of every NEVI-funded port to be $149,667. The federal government covers 80% of that, so its share comes out to $119,733. Even when that’s on the low finish, you’re taking a look at a authorities spend within the a whole bunch of hundreds of {dollars} for every station—not a whole bunch of thousands and thousands or billions.
Whereas we’re at it, it couldn’t damage to shortly tackle another elements of Trump’s latest Atlanta speech that handled EV charging. “There’s no means you may ever load them up,” he stated, referring to charging EVs. “They name it ‘loading’ them. You’ll be able to’t load ‘em. We’re going to should spend $9 trillion.”
First off, as one in all “them,” I can safely say no person calls charging “loading.”
Second, the Nationwide Renewable Power Laboratory estimates that the U.S. will want someplace between $53 billion and $127 billion in private and non-private EV charging investments by 2030 to assist the rising fleet of electrical automobiles. That’s loads, nevertheless it’s additionally not $9 trillion. Or $5 trillion, or $12 trillion, that are different numbers Trump has thrown round on this context.
Trump additionally defined to the Atlanta crowd that “a charger is a gasoline pump with electrical energy coming by it.” Really, that’s not a nasty means of describing it. I am going to give him that one.